The price of certainty: getting revenue models right for the UK's next generation of infrastructure

The UK does not appear to have a shortage of capital looking for infrastructure opportunities, but capital availability alone does not mean projects are investable.
That was one of my main reflections from last week's IPFA discussion on revenue models for the future of UK infrastructure. As projects become larger, technologies evolve and government places greater emphasis on affordability and energy security, the question is increasingly not simply where investment will come from, but what balance of risk and return will allow that investment to be deployed.
Revenue models sit at the heart of this.
Certainty has a value
From a perspective, we can look to the basic principle of lower risk supporting a lower cost of capital – greater certainty over future cash flows can reduce lender risk, support greater debt capacity and lower the overall cost of capital.
The Regulated Asset Base (RAB) model demonstrates this well. For large, long-term infrastructure, it can provide predictable revenues while helping manage construction and delivery risk. The Thames Tideway Tunnel was highlighted during the discussion as an example of a project that remained liquid and attractive to investors despite significant construction cost pressures.
It’s a model that has been deployed time and again across major utilities projects, and one that the district heating industry is increasingly looking towards as a route for reducing risks around committing hundreds of millions in upfront capital expenditure without the payback through revenues from connections for potentially several years. This challenge has until now meant that large-scale projects rely on equity funding with a high return requirement to be met, with grant funding the only typical route for mitigating this.
Contracts for Difference (CfDs) also provide certainty, effectively guaranteeing the strike price for the generator by settling the difference between that and the market price paid by purchasers of energy. By reducing exposure to wholesale electricity prices, they have played an important role in making UK renewable projects financeable, as lenders are more comfortable lending at a lower cost of capital, and indeed in the current environment suppliers are making payments to Government, so lowering everyone’s bills.
Corporate PPAs can provide another long-term hedge, while cap-and-floor mechanisms seek to protect investors against extreme downside, thus offering a debt-friendly environment while retaining some exposure to market performance.
This is not to say there is an inherently ‘right’ model, as each makes a different choice about where risk sits between investors, lenders, government and consumers, and project-specific dynamics will always come into play.
Revenue certainty does not equal bankability
It is important to recognise that revenue certainty does not by default equate to project bankability, and this is particularly the case for emerging technologies. A project can have an attractive revenue mechanism and still struggle to reach financial close – take floating offshore wind for example, where a CfD may be secured but technology, construction, supply-chain, inflation or delivery risk are not removed, and may all delay or halt the entire project.
This was seen clearly in AR5, where no wind projects from that rounded ended up being developed, widely seen as resulting from strike prices being too low relative to the prevailing cost of developing the projects – revenue certainty did in fact not mean economic viability. Whilst later rounds have recovered from this and led to far more successful outcomes, the recently announced pause on AR9 will also introduce renewed uncertainty across the sector. The same applies to grid delays. If generation is ready before the network that is needed to connect it, allocating that risk entirely to the generator can undermine project economics even where revenues themselves are relatively predictable.
When we model infrastructure investments, the interaction between these risks matters as much as the headline revenue mechanism. The length and structure of support, merchant exposure, construction delays and counterparty risk can all materially affect debt capacity, equity returns and ultimately the price required from consumers.
The cheapest model is not always the lowest-cost model
Perhaps the most difficult part of the debate is affordability. Keeping costs down for consumers is rightly a priority, but pursuing the lowest possible headline price does not necessarily deliver infrastructure at the lowest whole-life cost.
Revenue certainty and government support have a cost, but they can also lower financing costs and unlock investment that otherwise might not happen. RAB illustrates the tension particularly clearly – asking consumers to contribute during construction can be politically difficult, but doing so can reduce financing requirements and therefore the project's lifetime cost.
The same challenge can be seen in supply chains, where putting capital into manufacturing capacity before projects reach final investment decision requires funding upfront but without that investment, constraints further down the line can increase costs or prevent projects progressing at all.
This goes to show that we need to be explicitly discussing whole-life value alongside visible and upfront costs of support, thinking about risk through what gets built and when it is delivered, who bears the risk and what that ultimately costs.
Capital has choices
The final consideration is that, whilst there is no shortage of infrastructure capital in the UK, that capital is not captive.
UK projects compete internationally for institutional equity, infrastructure funds, bank debt and other sources of capital. If investors are expected to absorb greater construction, merchant, regulatory or grid risk without sufficient compensating return, there are other markets in which that capital can be deployed.
As the UK's infrastructure requirements increase, getting the revenue model right will therefore matter just as much as attracting the capital itself – RAB, CfDs, cap-and-floor mechanisms, corporate PPAs and merchant revenues all have different roles, and increasingly we may see projects move between or combine them over their lifecycle.
The challenge is to create enough certainty to attract capital at an efficient cost, while leaving risk with those genuinely best placed to manage it.